Robotics & Autonomous Systems

Find out more about our robotics and autonomous systems testing and validation facilities.

Find out more

Electrical Infrastructure Research Hub

The Catapult has appointed the University of Strathclyde and the University of Manchester to form the Electrical Infrastructure Research Hub.

Find out more

Automation & Engineering Solutions

Find out more about our work in robotics, autonomous systems and artificial intelligence.

Find out more

Stay Current

Dig deeper into the biggest issues facing offshore wind, wave and tidal energy with our series of Analysis & Insight papers.

Find out more

Live Innovation Opportunities

There are a number of programmes laying out the key technology innovation challenges faced by the offshore renewables industry that, when solved, will help drive down the cost of offshore renewable energy, with positive effects for the industry and UK economy. Visit our Live Innovation Opportunities page to find out if your technology has the answer.

Find out more

Cutting edge lab upgrade increases 66 kV deployment potential

The Offshore Renewable Energy (ORE) Catapult has upgraded its UKAS accredited high voltage (HV) electrical laboratory, providing enhanced testing capability unique in the UK and paving the way for an industry shift from 33 kV to 66 kV for future offshore wind inter-array electrical systems.

The upgrade to the adjustable HV reactor involved introducing an automated control system and increasing the power rating of the 600 kV resonant transformer, in collaboration with Doble PowerTest, to 150 kW of power. This now means that the reactor has both the required high voltage and power capacity to carry out automated step-breakdown testing of 66 kV cable systems using water terminations.

ORE Catapult’s HV electrical test laboratory is capable of exerting up to twenty times the operating stresses on the cable. This type of Highly Accelerated Lifetime Test (HALT) is used to instigate breakdown across the cable insulation, enabling the qualification of new wet-type cable systems and the assessment of the degradation of cable insulation systems.

Stepping up array systems in offshore wind farms to 66 kV will have a dramatic impact on the sector, enabling increased offshore power density, lower operational losses, fewer offshore collector substations and the resulting reduction in the levelised cost of energy. Ultimately, this move is essential for the development of larger offshore wind power parks which will use larger capacity offshore wind turbines.

Alex Neumann, Asset & Business Development Manager, ORE Catapult, commented:

“This upgrade represents a significant step-up for the HV laboratory, allowing the business to provide a unique service to the market. This new service enables the cost-effective development of new technology and complements the accelerated lifetime test work that we have developed with our clients to fast-track their product’s development and availability.”

Jeremy Featherstone, Product Development Director, JDR Cables, commented:

“This enhancement has played a significant role in supporting our development programme, allowing us to better predict the expected lifetime of the power cable, as well as validate and qualify its design. This capability will allow us to move to 66kV inter-array power supply which is a key driver to ensuring future offshore renewable energy development is cost-effective and reliable.”


Back to Press Releases

Published
Thu 18 Feb 2016
Last Updated
Tue 23 Jan 2018